To estimate concrete for a footing, calculate the volume of each footing section in cubic feet, add the sections together, and divide the total by 27 to convert cubic feet to cubic yards.
The math is straightforward. Getting the inputs right is the important part. Strip footings, isolated pads, round piers, grade beams, steps, and changes in depth should be measured separately so one simplified number does not hide a large error.
This guide explains how to estimate the concrete volume for common footing shapes before scheduling a delivery in New Braunfels, San Antonio, or elsewhere in Central Texas.
Important: A volume calculation does not design a footing. Use the dimensions, reinforcement, concrete strength, and details shown on the approved plans or provided by the responsible contractor or engineer.
Quick answer
Calculate each footing section in cubic feet, add the section volumes, and divide the total by 27 to convert cubic feet to cubic yards. Measure strip footings, pads, round piers, steps, grade beams, and depth changes separately, then compare the calculation with actual field conditions before ordering.
Separate the shapes
List every strip, pad, pier, grade beam, step, and depth change.
Calculate cubic feet
Use the rectangular or cylindrical volume formula with all dimensions in feet.
Add and convert
Add the section volumes and divide the total cubic feet by 27.
Verify the field
Compare plans with excavation, forms, access, and the project-specific allowance.
The Basic Cubic-Yard Formula
For any rectangular section:
Length in feet × width in feet × depth in feet = cubic feet
Cubic feet ÷ 27 = cubic yards
If width or depth is measured in inches, divide that number by 12 before multiplying.
For several identical footings:
Volume of one footing × quantity = total volume
For a round pier or drilled shaft:
3.1416 × radius² × depth = cubic feet
Cubic feet ÷ 27 = cubic yards
The radius is half the diameter. Keep every measurement in feet before completing the calculation.
Express Metered Concrete’s concrete calculator handles rectangular and round shapes and lets you add multiple project areas to one estimate.
How to Calculate a Continuous Strip Footing
A strip footing runs continuously under a wall or along a building perimeter. Use the total run length from the approved plan, then multiply it by the specified width and depth.
Example: 60-foot strip footing
Assume the plan shows:
- Total run: 60 feet
- Width: 18 inches, or 1.5 feet
- Depth: 10 inches, or approximately 0.833 feet
60 × 1.5 × 0.833 = approximately 75 cubic feet
75 ÷ 27 = approximately 2.78 cubic yards
The net geometric volume is approximately 2.78 cubic yards. This is not automatically the order quantity. The contractor should review the excavation, forms, plan details, and appropriate planning allowance before confirming delivery.
Avoid counting corners twice
For a rectangular perimeter, adding all outside wall lengths can count the corner volume twice. Use the footing lengths shown in the takeoff or measure one pair of walls outside-to-outside and the other pair between those walls. On an engineered project, follow the plan dimensions and estimator’s takeoff method.
How to Calculate Isolated Pad Footings
Pad footings support individual columns, posts, or piers. Calculate one pad, multiply by the number of identical pads, and create a separate calculation for every different size.
Example: four square pads
Assume each pad is:
- 3 feet long
- 3 feet wide
- 1 foot deep
- Quantity: 4
3 × 3 × 1 = 9 cubic feet per pad
9 × 4 = 36 cubic feet
36 ÷ 27 = approximately 1.33 cubic yards
The four pads have a combined net volume of approximately 1.33 cubic yards.
If two pads are larger or deeper, calculate those separately rather than averaging the sizes.
How to Calculate Round Pier Footings
For round holes or formed piers, use the volume formula for a cylinder. Measure the diameter and depth shown on the plan or verified in the field.
Example: twelve round piers
Assume each pier is:
- Diameter: 18 inches, or 1.5 feet
- Radius: 0.75 feet
- Depth: 3 feet
- Quantity: 12
3.1416 × 0.75 × 0.75 × 3 = approximately 5.30 cubic feet per pier
5.30 × 12 = approximately 63.62 cubic feet
63.62 ÷ 27 = approximately 2.36 cubic yards
The twelve piers have a combined net volume of approximately 2.36 cubic yards.
Drilled holes can widen, collapse, or vary in depth. Field measurements should be compared with the plan before the order is finalized.
How to Combine Several Footing Types
Many foundation placements include more than one shape. Keep the takeoff organized by section:
| Section | Net volume |
|---|---|
| Continuous strip footing | 2.78 yd³ |
| Four square pads | 1.33 yd³ |
| Twelve round piers | 2.36 yd³ |
| Combined net volume | 6.47 yd³ |
This example produces a net geometric volume of 6.47 cubic yards before any project-specific planning allowance. The actual project should use its own dimensions, field conditions, and supplier coordination.
What Changes a Footing Estimate in the Field?
Excavation is wider than the plan
Footings cast directly against earth may use more concrete when the trench sides are irregular, soil falls into the excavation, or the equipment cuts beyond the planned width.
Depth varies
Soft areas, stepped footings, grade changes, and over-excavation can add volume. Measure each depth change as a separate section instead of using the shallowest dimension across the entire run.
Forms move or bow
Forms should be complete, braced, and inspected before concrete arrives. A form that spreads during placement changes both the volume and the finished geometry.
The plan includes grade beams or thickened sections
Do not estimate only the visible perimeter if the foundation also includes interior grade beams, column pads, turned-down edges, or equipment bases. Add each component once and check for overlapping geometry.
The truck cannot discharge near the forms
Placement access does not change the geometric volume, but it affects scheduling and equipment. If the chute cannot reach the footing, coordinate a bucket, conveyor, or concrete pumping plan before delivery day.
How Much Extra Concrete Should You Plan?
There is no universal allowance that fits every footing. Formed pads on a controlled base may be close to their calculated dimensions. Earth-formed trenches with irregular soil can vary much more.
The contractor should choose an allowance based on:
- The difference between planned and measured excavation
- Whether the footing is earth-formed or formed on all sides
- Soil stability and recent weather
- The number of steps, corners, and irregular sections
- Placement losses and pump-line requirements when applicable
- The supplier’s delivery method and available capacity
Metered volumetric delivery can reduce the risk of paying for a large unused balance because concrete is produced and measured at the jobsite. It does not eliminate planning. A volumetric truck still has finite material capacity, and large or continuous placements must be coordinated in advance.
Design Dimensions and Volume Are Different Questions
A calculator can tell you the volume of dimensions you enter. It cannot determine the correct footing width, depth, reinforcement, bearing capacity, or concrete strength.
The International Residential Code ties footing dimensions to factors such as structural loads and the soil’s load-bearing value. Local amendments, engineered plans, floodplain conditions, and project-specific requirements may also apply.
New Braunfels lists foundations among work requiring a permit. San Antonio’s inspection requirements include checking footing excavations and required reinforcing before concrete placement. Confirm the current permit and inspection requirements with the authority responsible for the project.
Footing Delivery Checklist
Before confirming the order, verify:
- The latest approved plan and footing schedule are being used.
- All strip, pad, pier, grade-beam, and thickened sections are included once.
- Inches have been converted to feet correctly.
- Field measurements match the planned excavation and forms.
- Required inspections are complete before placement.
- Reinforcement, dowels, sleeves, embeds, and blockouts are installed.
- Forms are braced and the excavation is ready.
- The concrete mix matches the project specification.
- The truck-access and placement route are clear.
- The crew, tools, consolidation equipment, and weather protection are ready.
- The planned delivery rate matches the crew’s placement rate.
- The supplier has the job location, quantity, schedule, access notes, and placement method.
For continuous placements, also review the guide to preventing cold joints in concrete.
Frequently Asked Questions
How many cubic feet are in one cubic yard of concrete?
One cubic yard contains 27 cubic feet. After calculating the footing volume in cubic feet, divide by 27.
Do I subtract the volume of reinforcing steel?
Typical ordering estimates generally use the full geometric volume of the footing rather than attempting to subtract each reinforcing bar. Follow the estimator, contractor, or supplier’s method for the project.
Can the ExpressMC calculator estimate strip footings?
Yes. Enter the strip footing as a rectangular area using the total run, width, and depth. Add separate areas for pads, piers, steps, grade beams, or sections with different dimensions.
Does the calculator tell me the correct footing size?
No. It calculates the volume of the dimensions entered. Footing design should come from the approved plans, applicable code, contractor, or engineer.
Can metered concrete help if my estimate is slightly off?
On-site metered production can match the volume placed more closely than ordering only in fixed loads. The truck’s material capacity and the overall placement plan still matter, so give the supplier a careful estimate before scheduling.
Request Concrete for Footings in Central Texas
Express Metered Concrete supplies fresh, metered concrete for footings, foundations, pads, piers, and other residential or commercial placements across New Braunfels, San Antonio, and surrounding communities.
Use the concrete volume calculator for a planning estimate, then request a concrete quote with the project location, approved mix, estimated volume, placement method, access conditions, and preferred schedule.
References and further reading
These primary and industry sources support the planning concepts in this guide. Project plans, specifications, permits, and the responsible professionals still control the work.